LED S-W-157(001)-1 OAK HARBOR LED Streetlight Conversion Construction 03/31/2021 49
UAP 8-2-018(010)-1 KITSAP COUNTY SE Lund Avenue Design 03/31/2022 37
ATP P-W-190(P03)-1 HOQUIAM City of Hoquiam Safe Routes to School Construction 12/20/2022 28
ATP P-W-126(P05)-1 SEDRO WOOLLEY Cascade Trail West Extension Phase 2A Design 12/16/2022 28
UAP 8-2-156(043)-1 BELLINGHAM Meridian St Construction 01/18/2023 27
ATP P-P-113(P03)-1 FEDERAL WAY Citywide Pedestrian Crossings Design 01/23/2023 27
ATP P-E-897(P10)-2 MEDICAL LAKE Lefevre Street Restriping and Sidewalk Design 02/23/2023 26
LED S-W-158(001)-1 POULSBO LED Streetlight Conversion Construction 06/09/2023 22
UAP 8-4-177(011)-1 COLLEGE PLACE SW Mojonnier Road Improvements Design 12/19/2023 16
SCAP 6-W-838(009)-1 EVERSON S Harkness Street Design 12/22/2023 16
SCAP 6-W-825(009)-1 FORKS West E Street Design 12/12/2023 16
UAP 8-1-118(003)-1 LAKE FOREST PARK SR 104 Design 12/15/2023 16
LED S-W-153(001)-1 PORT ORCHARD LED Streetlight Conversion Construction 12/07/2023 16
UAP 8-2-158(009)-1 POULSBO Noll Road - Segment 3A Construction 12/18/2023 16
ATP P-P-142(P01)-1 SNOHOMISH 13th Street Intersection Improvements Design 12/14/2023 16
ATP P-P-031(P03)-1 SNOHOMISH COUNTY Puget Park Drive RRFBs Construction 12/13/2023 16
ATP P-W-830(P02)-1 BAINBRIDGE ISLAND NE Wyatt Way Design 01/29/2024 15
ATP P-E-848(P07)-1 CHELAN Resin Bonded Stone Surfacing Pilot Construction 01/11/2024 15
SCAP 6-E-848(I07)-1 CHELAN Sanders Street Pedestrian Improvements Design 01/11/2024 15
ATP P-P-111(P08)-1 KIRKLAND Pedestrian Crossing at Lake Washington Institute of Technology Construction 01/24/2024 15
UAP 8-2-018(012)-1 KITSAP COUNTY Lund Avenue Roundabout Design 01/02/2024 15
ATP P-P-117(P02)-1 PACIFIC Interurban Trail Crossing Improvements Design 01/23/2024 15
UAP 8-5-948(006)-1 BATTLE GROUND SE Grace Avenue - Phase II Design 02/22/2024 14
UAP 8-2-156(045)-1 BELLINGHAM 12th Street and Finnegan Way Construction 02/06/2024 14
UAP 8-3-004(003)-1 CHELAN COUNTY Easy St and School St Intersection Design 02/02/2024 14
SCAP 6-E-166(003)-1 MILLWOOD Argonne Road Reconstruction - Phase 2 Design 02/27/2024 14
ATP P-P-804(P09)-1 NORTH BEND SR202 Sidewalk Gap Construction 02/05/2024 14
SCAP 6-E-853(I02)-1 ROCK ISLAND Douglas Street Improvements Design 02/19/2024 14
SCAP 6-W-951(001)-1 YACOLT W Hoag Street Design 02/16/2024 14
UAP 8-5-194(012)-1 SHELTON Olympic Highway North Design 03/20/2024 13
SCAP 6-E-946(007)-1 WAPATO N Ahtanum Avenue Reconstruction Design 03/22/2024 13
LED S-P-813(001)-1 ORTING LED Streetlight Conversion Construction 04/24/2024 12
LED S-P-136(001)-1 BONNEY LAKE LED Streetlight Conversion Construction 05/24/2024 11
UAP 8-2-150(010)-1 PORT ANGELES 8th Street Construction 05/22/2024 11
SCAP 6-W-974(I08)-1 STEVENSON 1st Street Construction 05/22/2024 11
UAP 8-5-185(010)-1 CAMAS NW 38th Avenue Construction 06/23/2024 10
ATP P-P-143(P03)-1 MARYSVILLE 53rd Ave NE Shared Used Path Construction 07/24/2024 9
UAP 8-5-195(017)-1 OLYMPIA Fones Road SE Construction 07/25/2024 9
SCAP 6-W-957(I14)-1 MONTESANO Lake Sylvia Road Sidewalk Construction 08/05/2024 8
UAP 8-1-141(008)-1 MOUNTLAKE TERRACE 66th Avenue W Construction 08/05/2024 8
UAP 8-3-165(092)-1 SPOKANE Maple Street and Walnut Street Construction 08/19/2024 8
UAP 8-5-196(018)-1 TUMWATER Capitol Boulevard South, Trosper Road SE Construction 08/05/2024 8
UAP 8-3-893(007)-1 AIRWAY HEIGHTS 6th Avenue Construction 09/23/2024 7
UAP 8-2-154(016)-1 ANACORTES Commercial Avenue (SR 20 Spur) Design 09/20/2024 7
SCAP 6-P-801(011)-1 CARNATION McKinley Street Construction 09/20/2024 7
UAP 8-5-187(017)-1 LONGVIEW 46th Avenue Construction 09/12/2024 7
ATP P-W-956(P07)-1 MCCLEARY W Maple Street Sidewalk Design 09/18/2024 7
SCAP 6-W-958(001)-1 OAKVILLE School Street and W Pine Street Design 09/05/2024 7
ATP P-P-129(P02)-1 PUYALLUP 7th Street Sidewalk Design 10/01/2024 7
UAP 8-3-165(091)-2 SPOKANE Thor / Freya Couplet Construction 09/30/2024 7
UAP 8-3-009(012)-1 DOUGLAS COUNTY 21st St NE Design 10/30/2024 6
ATP P-P-027(P09)-1 PIERCE COUNTY 2025 RRFB School Crossing Construction 10/10/2024 6
ATP P-P-102(P03)-1 RENTON S 7th Street Improvements Construction 10/14/2024 6
ATP P-P-806(P04)-1 SNOQUALMIE 384th Ave SE Sidewalk Construction 10/02/2024 6
SP P-E-165(P10)-1 SPOKANE Haven Street Sidewalk Construction 10/29/2024 6
UAP 8-1-131(008)-1 SUMNER Stewart Road White River Bridge Construction 10/28/2024 6
UAP 8-3-160(031)-1 WENATCHEE Springwater Avenue Construction 10/22/2024 6
SCAP 6-E-901(009)-1 CHEWELAH W Main Avenue Construction 11/20/2024 5
UAP 8-4-177(010)-1 COLLEGE PLACE NE Damson Avenue Construction 11/14/2024 5
SCAP 6-W-953(012)-1 KALAMA China Garden Road Construction 11/21/2024 5
SCAP 6-E-882(011)-1 OROVILLE Ironwood Street Construction 11/05/2024 5
UAP 8-4-174(020)-1 PASCO Lewis Street Construction 11/19/2024 5
UAP 8-5-950(002)-1 RIDGEFIELD S Royle Road Construction 11/04/2024 5
SP P-P-101(P08)-1 SEATTLE 4th Avenue S Walkway Construction 11/05/2024 5
SCAP 6-E-865(006)-1 SOAP LAKE Canna Street and 1st Avenue NE Construction 11/04/2024 5
SCAP 6-E-865(007)-1 SOAP LAKE Main Avenue W Construction 11/04/2024 5
UAP 8-4-180(027)-1 YAKIMA 34th Avenue Roundabouts Construction 11/25/2024 5
UAP 8-3-893(006)-1 AIRWAY HEIGHTS 10th Avenue Extension Construction 12/16/2024 4
UAP 8-3-161(015)-1 EAST WENATCHEE 19th Street NW Phase 1 Construction 12/04/2024 4
UAP 8-1-113(013)-1 FEDERAL WAY S 288th Street Construction 12/06/2024 4
SCAP 6-E-942(004)-1 MABTON Main Street Reconstruction Project Construction 12/05/2024 4
ATP P-E-897(P10)-1 MEDICAL LAKE Lefevre Street Restriping and Sidewalk Construction 12/16/2024 4
ATP P-P-822(P04)-1 MONROE RRFB Crossings Construction 12/18/2024 4
ATP P-E-886(P02)-1 TWISP North End SR 20 PedestrianBike Path Construction 12/17/2024 4
SCAP 6-W-960(006)-1 WESTPORT N Forrest Street Construction 12/05/2024 4
UAP 8-1-110(009)-1 DES MOINES 24th Avenue S Construction 01/16/2025 3
ATP P-E-883(P05)-1 PATEROS Downtown ADA Improvements Construction 01/07/2025 3
ATP P-E-883(P06)-1 PATEROS Resin Bonded Stone Surfacing Pilot Construction 01/07/2025 3
UAP 8-2-158(010)-1 POULSBO Noll Road Phase 3B Construction 01/30/2025 3
UAP 8-1-102(038)-1 RENTON Rainier Avenue S/N Construction 01/29/2025 3
UAP 8-3-160(032)-1 WENATCHEE McKittrick Street Construction 01/22/2025 3