City of Newcastle's SE May Creek Park Drive NonMotorized Improvements Phase 2

P-P-200(P01)-1

P-P-200(P01)-1
SE May Creek Park Drive NonMotorized Improvements Phase 2

SE 84th Pl to 129th Ave SE

FY 2026 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $489,010

County: King   |   Legislative District: 41   |   Project Length: 2,200.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 04/24/2026

Project Information

Lead Agency NEWCASTLE
Funding Year 2026
Program ATP
Current Phase Construction
Legislative District 41
Congressional District 9
Federal Route Number 1338
Project Length 2200.00 mi.
ADT 1,800
Functional Class Collector
Type of Work Pedestrian
Project Contact Kerry Sullivan
Contact Email kerrys@newcastlewa.gov
TIB Engineer Greg Armstrong
Last Payment Date 04/24/2026
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 01/01/2026  
DAHP Assessment Date   01/10/2025
Predesign Approval
Design Approval 01/01/2025 12/20/2024
Bid Auth. Approval 05/05/2025 05/22/2025
Construction Approval 07/02/2025 07/02/2025
Project Closeout 06/30/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 45,455 26,450
Construction Contract 454,545 2,158,735
Other Construction 0 0
Total Construction 500,000 2,185,185
     
Funding Surplus - 10,990  
Total TIB Funding 489,010 2,185,185

Local Funding Partners

Funding Amount Percent
NEWCASTLE 1,683,170 77.1%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 1,683,170 77.1%

Project Description

Widens the road to provide two 10-foot wide travel lanes a 6-foot bike lane along with curb, gutter and sidewalks the northeast side of the road.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.