Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Town of Cathlamet's S 3rd Street Sidewalk

P-W-979(001)-1

P-W-979(001)-1
S 3rd Street Sidewalk

Maple St to Alder St

FY 2026 Active Transportation Program
Current Phase : Bid Authorization
Total TIB Funding : $224,887

County: Wahkiakum   |   Legislative District: 19   |   Project Length: 630.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency CATHLAMET
Funding Year 2026
Program ATP
Current Phase Bid Authorization
Legislative District 19
Congressional District 3
Federal Route Number 9999
Project Length 630.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Sarah Clark
Contact Email projectmanager@townofcathlamet.com
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date   09/18/2025
Predesign Approval
Design Approval 01/01/2025 12/17/2024
Bid Auth. Approval 04/30/2026 04/03/2026
Construction Approval 05/15/2026
Project Closeout 12/01/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 25,947 25,947
Right of Way 0 0
Total Design 25,947 25,947
     
Construction Engineering 25,950 25,950
Construction Contract 172,990 172,990
Other Construction 0 0
Total Construction 198,940 198,940
     
Total TIB Funding 224,887 224,887

Local Funding Partners

Funding Amount Percent
CATHLAMET 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

This project creates a safe, connected and accessible sidewalk on the north side of S. 3rd St. in front of Julius A. Wendt Elementary School campus, connecting to the Wahkiakum High School campus, separating children and foot traffic from school buses and other moving vehicles.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments