City of Snohomish's 13th Street Intersection Improvements

P-P-142(P01)-1

P-P-142(P01)-1
13th Street Intersection Improvements

Park Ave

FY 2025 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $172,891

County: Snohomish   |   Legislative District: 44   |   Project Length: 150.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 11/18/2025

Project Information

Lead Agency SNOHOMISH
Funding Year 2025
Program ATP
Current Phase Construction
Legislative District 44
Congressional District 1
Federal Route Number 2650
Project Length 150.00 mi.
ADT 5,100
Functional Class Collector
Type of Work Pedestrian
Project Contact Siobhan Waltman
Contact Email Waltman@snohomishwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 11/18/2025
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2024 12/14/2023
Bid Auth. Approval 02/05/2026 02/11/2026
Construction Approval 03/12/2026 03/23/2026
Project Closeout 07/31/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 8,454 3,755
Right of Way 0 0
Total Design 8,454 3,755
     
Construction Engineering 2,125 10,500
Construction Contract 166,960 209,147
Other Construction 0 0
Total Construction 169,085 219,647
     
Funding Surplus - 4,648  
Total TIB Funding 172,891 223,402

Local Funding Partners

Funding Amount Percent
SNOHOMISH 50,511 22.6%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 50,511 22.6%

Project Description

This project will construct curb bulb outs on 13th Street at Pine Aveune to increase visibility of pedestrians and reduce the crossing distance. adding rectangular rapid flashing beacons and additional street lighting will also be installed on the eastern leg of the intersection to further increase pedestrian safety.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.