 Planning —  Agency Assessment

TIB Annual Assessment

Measure 2014 2015 2016 2017 2018 Historic Data Trend
Percent Reduced Collisions on Arterials 18.12% 15.55% 16.02% 16.75% 17.89%
Percent of Small Cities with an Average PCR Score above 70 76.4% 71.5% 67.9% 72.9% 73.5%
Projects Completed 159 134 123 254 208
Projects Awarded 82 186 171 344 174
Miles of Roadway Awarded with Sidewalk Added 17.92 14.04 18.02 15.12 19.03
Miles of Resurfacing Awarded 18.07 49.09 50.84 32.94 51.7
Miles of Urban Street Extension or Improvement Awarded 10.94 14.96 17.51 17.23 14.16
Miles of Urban Roadway Awarded with Bikelanes Added 8.72 11.75 9.74 9.01 9.77
Average Number of Points Achieved in Sustainability 9 10.03 10.85 9.42 7.8
Agencies Without Awards in the Past 7 Years 41 40 34 26 24
Number of Projects not Billing in Last Calendar Year 24 44 67 60 28
Percent of Dollars Spent on Design 11.78% 9.4% 10.12% 9.99% 9.71%
Percent of Dollars Spent on Construction 88.22% 90.6% 89.88% 90.01% 90.29%
Percent of Transactions Processed Within Target 99.17% 96.82% 99.72% 99.54% 99.34%
Number of Active Projects 349 387 428 480 476
Total Outstanding Obligation $309.0M $337.0M $348.0M $340.0M $337.6M
Fund Balances - TIA $37.6M $43.1M $47.2M $31.5M $15.2M
Fund Balances - SCPSA $1.5M $1.7M $2.1M $1.5M $1.5M
Average Age of Active Projects - Urban 2.14 1.76 1.87 1.94 1.83
Average Age of Active Projects - Small City 1.49 0.84 0.98 0.92 1.07
Number of Delayed Projects 2 3 1 4 1