Olive Street is a major collector and land use transitioning to residential housing. Sidewalks gaps exist on Olive and concerns exist with crossings at Olive/Chase Intersection which is a school walk route. Maple Street is missing a short section of sidewalk that needs to be added.
Projects — TIB Project Information
TIB Project Information
City of Cashmere's Sidewalk Improvements
P-E-847(P01)-1
P-E-847(P01)-1
Sidewalk Improvements
City of Cashmere
FY 2026 Active Transportation Program
Current Phase : Bid Authorization
Total TIB Funding : $650,256
County: Chelan | Legislative District: 12 | Project Length: 1,000.00 | TIB Engineer: Andrew Beagle | Last Payment Date: 03/03/2026
Project Information
| Lead Agency | CASHMERE |
| Funding Year | 2026 |
| Program | ATP |
| Current Phase | Bid Authorization |
| Legislative District | 12 |
| Congressional District | 8 |
| Federal Route Number | 9999 |
| Project Length | 1000.00 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Pedestrian |
| Project Contact | Steve Croci |
| Contact Email | steve@cityofcashmere.org |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | 03/03/2026 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/22/2024 | |
| Delayed Project Date | 07/01/2027 | |
| DAHP Assessment Date | 03/09/2026 | |
| Predesign Approval | ||
| Design Approval | 02/17/2025 | 12/17/2024 |
| Bid Auth. Approval | 01/02/2026 | 03/24/2026 |
| Construction Approval | 05/15/2026 | |
| Project Closeout | 12/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 56,653 | 59,635 |
| Right of Way | 0 | 0 |
| Total Design | 56,653 | 59,635 |
| Construction Engineering | 56,653 | 59,635 |
| Construction Contract | 536,950 | 565,210 |
| Other Construction | 0 | 0 |
| Total Construction | 593,603 | 624,845 |
| Total TIB Funding | 650,256 | 684,480 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| CASHMERE | 34,224 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 34,224 | 5.0% |
Project Description
Olive Street sidewalk infill, mprove stormwater management, add crosswalk with flashing beacons at the Chase Street Intersection. Maple Street sidewalk infill.
Existing Condition
Project Benefits
- Maple Street connects Cashmeres biggest and most used park to the adjacent neighborhood and the Central Business District. Olive street is a school walk route.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||