City of Tacoma
Port of Tacoma Road
E 11th Street to Marshall Avenue
The City of Tacoma's Port of Tacoma Road project was selected for funding in November 2014. TIB contributed $6,364,494 in funding toward the $9,237,820 total cost of the project.
This project will replace the failing asphalt with a ten-inch cement concrete pavement surface from curb to curb. ADA ramps and driveways will be upgraded as needed, curb and gutter will be replaced as needed. The temporary signal near Lincoln Avenue will be replaced with a permanent signal, and the railroad will partner with the city to replace the railroad crossing and tracks.
More Project Information
- View Detailed Project Information
- View the Project Map
- TIB Engineer for this project: Greg Armstrong