TIB Project Information

City of Tacoma's Port of Tacoma Road

8-1-128(093)-1

8-1-128(093)-1
Port of Tacoma Road

E 11th Street to Marshall Avenue

FY 2016 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $6,689,494

County: Pierce   |   Legislative District: 27   |   Project Length: 0.66   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 01/17/2017

Project Information

Lead Agency TACOMA
Funding Year 2016
Program UAP
Current Phase Audit
Legislative District 27
Congressional District 9
Federal Route Number 3143
Project Length 0.66 mi.
ADT 11,106
Functional Class Principal
Type of Work
Project Contact Tom Rutherford
Contact Email trutherford@cityoftacoma.org
TIB Engineer Greg Armstrong
Last Payment Date 01/17/2017
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2014
Delayed Project Date 07/01/2019  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2015 12/16/2014
Bid Auth. Approval 01/15/2015 01/15/2015
Construction Approval 04/01/2015 03/31/2015
Project Closeout 08/31/2016 12/29/2016
Audit Date   01/17/2017
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 774,900 651,450
Construction Contract 5,165,800 9,657,416
Other Construction 0 49,081
Total Construction 5,940,700 10,357,947
     
Funding Increase 748,794  
Total TIB Funding 6,689,494 10,357,947

Local Funding Partners

Funding Amount Percent
TACOMA 1,583,973 15.3%
WSDOT Funding 0 0.0%
Port of Tacoma  944,890 9.1%
Tacoma Rail  139,590 1.3%
FMSIB  1,000,000 10.8%
 
 
 
 
 
Total Local Funding 3,668,453 0.0%

Project Description

This project will replace the failing asphalt with a ten-inch cement concrete pavement surface from curb to curb. ADA ramps and driveways will be upgraded as needed, curb and gutter will be replaced as needed. The temporary signal near Lincoln Avenue will be replaced with a permanent signal, and the railroad will partner with the city to replace the railroad crossing and tracks.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments