67th Avenue is a two-lane arterial with narrow shoulders and discontinuous sidewalks. There are multiple clear zone issues and the pavement is in poor condition.
TIB Project Information
City of Arlington's 67th Avenue NE/E Maple Street
9-P-817(004)-1
9-P-817(004)-1
67th Avenue NE/E Maple Street
204th St to Olympic Ave
FY 2013 Urban Corridor Program
Current Phase : Audit
Total TIB Funding : $6,061,270
County: Snohomish | Legislative District: 39 | Project Length: 1.03 | TIB Engineer: Greg Armstrong | Last Payment Date: 08/01/2014
Project Information
Lead Agency | ARLINGTON |
Funding Year | 2013 |
Program | UCP |
Current Phase | Audit |
Legislative District | 39 |
Congressional District | 2 |
Federal Route Number | 2699 |
Project Length | 1.03 mi. |
ADT | 2,699 |
Functional Class | Principal |
Type of Work | Major Widening |
Project Contact | Eric Scott |
Contact Email | escott@arlingtonwa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 08/01/2014 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2011 | |
Delayed Project Date | 01/01/2013 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | ||
Bid Auth. Approval | 06/04/2012 | 06/01/2012 |
Construction Approval | 03/01/2013 | 03/05/2013 |
Project Closeout | 07/24/2014 | 07/16/2014 |
Audit Date | 08/01/2014 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 1,107,778 |
Construction Contract | 6,049,731 | 6,514,394 |
Other Construction | 0 | 414,552 |
Total Construction | 6,049,731 | 8,036,724 |
Funding Increase | 219,679 | |
Funding Surplus | - 208,140 | |
Total TIB Funding | 6,061,270 | 8,036,724 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ARLINGTON | 715,246 | 8.9% |
WSDOT Funding | 0 | 0.0% |
Mitigation Dollars | 1,002,505 | 12.5% |
STP Funds | 257,703 | 3.2% |
Total Local Funding | 1,975,454 | 24.6% |
Project Description
This project will reconstruct and widen 67th Avenue to provide two travel lanes, a two-way left turn lane, a 6-foot sidewalk on the west side and a 12-foot multi-use path on the east side of the roadway. A new traffic signal will be installed at the 211th Street intersection along with right turn pockets.
Existing Condition
Project Benefits
- Improves safety;
- Increases capacity;
- Completes gap in non-motorized facilities
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |