Edison Street is a four-lane arterial with curb, gutter and sidewalks. There are no turning lanes or accommodations for bicycles.
TIB Project Information
City of Kennewick's Edison Street
8-4-173(028)-1
8-4-173(028)-1
Edison Street
Clearwater Ave to Canal Dr
FY 2012 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $1,165,522
County: Benton | Legislative District: 8 | Project Length: 0.60 | TIB Engineer: Jonathan Heusman | Last Payment Date: 05/15/2017
Project Information
| Lead Agency | KENNEWICK |
| Funding Year | 2012 |
| Program | UAP |
| Current Phase | Audit |
| Legislative District | 8 |
| Congressional District | 4 |
| Federal Route Number | 3413 |
| Project Length | 0.60 mi. |
| ADT | 14,713 |
| Functional Class | Minor |
| Type of Work | Safety |
| Project Contact | Steve Plummer |
| Contact Email | steve.plummer@ci.kennewick.wa.us |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 05/15/2017 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/19/2010 | |
| Delayed Project Date | 07/01/2015 | |
| DAHP Assessment Date | 10/15/2015 | |
| Predesign Approval | ||
| Design Approval | 03/01/2011 | 03/22/2011 |
| Bid Auth. Approval | 10/01/2015 | 10/27/2015 |
| Construction Approval | 11/30/2015 | 12/01/2015 |
| Project Closeout | 11/30/2016 | 05/03/2017 |
| Audit Date | 05/15/2017 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 88,200 | 132,013 |
| Right of Way | 210,000 | 290,198 |
| Total Design | 298,200 | 422,211 |
| Construction Engineering | 88,200 | 146,243 |
| Construction Contract | 769,800 | 2,140,362 |
| Other Construction | 13,800 | 31,155 |
| Total Construction | 871,800 | 2,317,760 |
| Funding Surplus | - 4,478 | |
| Total TIB Funding | 1,165,522 | 2,739,971 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| KENNEWICK | 646,449 | 23.6% |
| WSDOT Funding | 0 | 0.0% |
| STP | 928,000 | 33.7% |
| Total Local Funding | 1,574,449 | 0.0% |
Project Description
This project will reconstruct the existing roadway to include four travel lanes, a center left-turn lane, bicycle lanes, curb and gutter, and sidewalks. Included in the project will be modification of the traffic signals at both ends.
Existing Condition
Project Benefits
- Improves safety;
- Completes corridor;
- Reduces congestion
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
| Schedule Issues Level 1 Board Delay |
10/27/2015 |