NE 85th Street is a very busy five-lane principal arterial with minimal transit and pedestrian facilities. Due to heavy congestion the two-way left turn lane functions poorly.
TIB Project Information
City of Kirkland's NE 85th Street (Construction Only)
8-1-111(018)-1
8-1-111(018)-1
NE 85th Street (Construction Only)
120th Ave NE to 132nd Ave NE
FY 2015 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $1,667,500
County: King | Legislative District: 48 | Project Length: 0.79 | TIB Engineer: Greg Armstrong | Last Payment Date: 08/15/2016
Project Information
| Lead Agency | KIRKLAND |
| Funding Year | 2015 |
| Program | UAP |
| Current Phase | Audit |
| Legislative District | 48 |
| Congressional District | 1 |
| Federal Route Number | 2082 |
| Project Length | 0.79 mi. |
| ADT | 37,457 |
| Functional Class | Principal |
| Type of Work | Reconstruction |
| Project Contact | Dave Snider |
| Contact Email | dsnider@kirklandwa.gov |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | 08/15/2016 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/22/2013 | |
| Delayed Project Date | 07/01/2018 | |
| DAHP Assessment Date | 03/05/2014 | |
| Predesign Approval | ||
| Design Approval | 01/01/2014 | 01/13/2014 |
| Bid Auth. Approval | 04/04/2014 | 04/03/2014 |
| Construction Approval | 05/08/2014 | 05/15/2014 |
| Project Closeout | 08/05/2016 | 08/03/2016 |
| Audit Date | 08/15/2016 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 11,476 | 53,500 |
| Construction Contract | 1,438,524 | 6,725,520 |
| Other Construction | 0 | 0 |
| Total Construction | 1,450,000 | 6,779,020 |
| Funding Increase | 217,500 | |
| Total TIB Funding | 1,667,500 | 6,779,020 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| KIRKLAND | 3,368,847 | 49.7% |
| WSDOT Funding | 0 | 0.0% |
| Impact Fees | 351,805 | 5.9% |
| Sound Transit | 1,390,868 | 38.6% |
| Total Local Funding | 5,111,520 | 94.2% |
Project Description
This project reconstructs NE 85th Street with four travel lanes, a center median, curb, gutter, a landscaped strip and seven-foot sidewalks. In addition, right turn lanes at key intersection traffic signals will be upgraded and connected to Kirkland's traffic management center.
Existing Condition
Project Benefits
- Improves safety;
- Restores structural condition;
- Relieves congestion;
- Removes ADA barriers;
- Increases access control
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||