No sidewalk currently exists. Pedestrians walk in the travel lanes with no protection from traffic.
TIB Project Information
City of Pateros's Warren Avenue
P-E-883(P02)-1
P-E-883(P02)-1
Warren Avenue
East of Chris St to Beach Street
FY 2015 Sidewalk Program
Current Phase : Audit
Total TIB Funding : $325,457
County: Okanogan | Legislative District: 12 | Project Length: 0.20 | TIB Engineer: Andrew Beagle | Last Payment Date: 12/28/2016
Project Information
Lead Agency | PATEROS |
Funding Year | 2015 |
Program | SP |
Current Phase | Audit |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.20 mi. |
ADT | 250 |
Functional Class | TIB Arterial |
Type of Work | Pedestrian |
Project Contact | Kerri Wilson/Jord Wilson |
Contact Email | pateros@swift-stream.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 12/28/2016 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2013 | |
Delayed Project Date | 07/01/2016 | |
DAHP Assessment Date | 04/10/2014 | |
Predesign Approval | ||
Design Approval | 01/01/2014 | 01/30/2014 |
Bid Auth. Approval | 04/01/2016 | 06/29/2016 |
Construction Approval | 07/15/2016 | 08/01/2016 |
Project Closeout | 12/31/2016 | 12/20/2016 |
Audit Date | 12/28/2016 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 37,354 | 41,914 |
Right of Way | 0 | 0 |
Total Design | 37,354 | 41,914 |
Construction Engineering | 37,353 | 39,933 |
Construction Contract | 261,218 | 255,107 |
Other Construction | 0 | 97 |
Total Construction | 298,571 | 295,136 |
Funding Increase | 10,751 | |
Funding Surplus | - 21,219 | |
Total TIB Funding | 325,457 | 337,050 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
PATEROS | 11,593 | 3.6% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 11,593 | 3.6% |
Project Description
The project constructs new curb, gutter and six-foot sidewalk on one side of the street. The sidewalk connects to existing sidewalk leading to the downtown area. Other improvements include installing ADA-compliant ramps and crosswalk striping.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Enhances access to schools and CBD;
- Extends the sidewalk system
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |