TIB Project Information

City of Port Townsend's Howard Street

9-W-151(006)-1

9-W-151(006)-1
Howard Street

S Park Avenue to Discovery Road

FY 2014 Urban Corridor Program
Current Phase : Audit
Total TIB Funding : $2,233,301

County: Jefferson   |   Legislative District: 24   |   Project Length: 0.33   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 04/16/2018

Project Information

Lead Agency PORT TOWNSEND
Funding Year 2014
Program UCP
Current Phase Audit
Legislative District 24
Congressional District 6
Federal Route Number 7625
Project Length 0.33 mi.
ADT 0
Functional Class Minor
Type of Work New Location
Project Contact David L. Peterson, PE
Contact Email dpeterson@cityofpt.us
TIB Engineer Chris Langhoff
Last Payment Date 04/16/2018
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2012
Delayed Project Date 07/01/2017  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2013 01/03/2013
Bid Auth. Approval 12/15/2015 12/16/2015
Construction Approval 06/01/2016 07/18/2016
Project Closeout 12/31/2016 04/05/2018
Audit Date   04/16/2018
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 262,986 847,687
Right of Way 93,193 335,785
Total Design 356,179 1,183,472
     
Construction Engineering 87,662 715,448
Construction Contract 1,753,237 2,735,849
Other Construction 102,922 20,839
Total Construction 1,943,821 3,472,136
     
Funding Surplus - 66,699  
Total TIB Funding 2,233,301 4,655,608

Local Funding Partners

Funding Amount Percent
PORT TOWNSEND 753,125 16.2%
WSDOT Funding 0 0.0%
Port Townsend Utlitiy Funds Water & Sewer  0 0.0%
Private Utilities  0 0.0%
CERB GRANT  300,000 6.3%
CERB LOAN  269,182 5.8%
 
 
 
Federal Funding  1,100,000 23.2%
Total Local Funding 2,422,307 52.8%

Project Description

This project constructs approximately 1,700 feet of new arterial street connecting SR 20 to Discovery Road. The street will have two travel lanes, bike lanes, curb, gutter, sidewalks, and planter strips. A new roundabout will be constructed at the intersection of Howard Street and Discovery Road.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.