TIB Project Information

City of Kennewick's Edison Street

8-4-173(028)-1

8-4-173(028)-1
Edison Street

Clearwater Ave to Canal Dr

FY 2012 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $1,165,522

County: Benton   |   Legislative District: 8   |   Project Length: 0.60   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 05/15/2017

Project Information

Lead Agency KENNEWICK
Funding Year 2012
Program UAP
Current Phase Audit
Legislative District 8
Congressional District 4
Federal Route Number 3413
Project Length 0.60 mi.
ADT 14,713
Functional Class Minor
Type of Work Safety
Project Contact Steve Plummer
Contact Email steve.plummer@ci.kennewick.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 05/15/2017
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2010
Delayed Project Date 07/01/2015  
DAHP Assessment Date   10/15/2015
Predesign Approval
Design Approval 03/01/2011 03/22/2011
Bid Auth. Approval 10/01/2015 10/27/2015
Construction Approval 11/30/2015 12/01/2015
Project Closeout 11/30/2016 05/03/2017
Audit Date   05/15/2017
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 88,200 132,013
Right of Way 210,000 290,198
Total Design 298,200 422,211
     
Construction Engineering 88,200 146,243
Construction Contract 769,800 2,140,362
Other Construction 13,800 31,155
Total Construction 871,800 2,317,760
     
Funding Surplus - 4,478  
Total TIB Funding 1,165,522 2,739,971

Local Funding Partners

Funding Amount Percent
KENNEWICK 646,449 23.6%
WSDOT Funding 0 0.0%
STP  928,000 33.7%
 
 
 
 
 
 
 
Total Local Funding 1,574,449 0.0%

Project Description

This project will reconstruct the existing roadway to include four travel lanes, a center left-turn lane, bicycle lanes, curb and gutter, and sidewalks. Included in the project will be modification of the traffic signals at both ends.

Project Pictures

Project Delays

Delay Type Resolution Date Comments
Schedule Issues
Level 1 Board Delay
10/27/2015

Project Payments