Edison Street is a four-lane arterial with curb, gutter and sidewalks. There are no turning lanes or accommodations for bicycles.
TIB Project Information
City of Kennewick's Edison Street
8-4-173(028)-1
8-4-173(028)-1
Edison Street
Clearwater Ave to Canal Dr
FY 2012 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $1,165,522
County: Benton | Legislative District: 8 | Project Length: 0.60 | TIB Engineer: Jonathan Heusman | Last Payment Date: 05/15/2017
Project Information
Lead Agency | KENNEWICK |
Funding Year | 2012 |
Program | UAP |
Current Phase | Audit |
Legislative District | 8 |
Congressional District | 4 |
Federal Route Number | 3413 |
Project Length | 0.60 mi. |
ADT | 14,713 |
Functional Class | Minor |
Type of Work | Safety |
Project Contact | Steve Plummer |
Contact Email | steve.plummer@ci.kennewick.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 05/15/2017 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2010 | |
Delayed Project Date | 07/01/2015 | |
DAHP Assessment Date | 10/15/2015 | |
Predesign Approval | ||
Design Approval | 03/01/2011 | 03/22/2011 |
Bid Auth. Approval | 10/01/2015 | 10/27/2015 |
Construction Approval | 11/30/2015 | 12/01/2015 |
Project Closeout | 11/30/2016 | 05/03/2017 |
Audit Date | 05/15/2017 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 88,200 | 132,013 |
Right of Way | 210,000 | 290,198 |
Total Design | 298,200 | 422,211 |
Construction Engineering | 88,200 | 146,243 |
Construction Contract | 769,800 | 2,140,362 |
Other Construction | 13,800 | 31,155 |
Total Construction | 871,800 | 2,317,760 |
Funding Surplus | - 4,478 | |
Total TIB Funding | 1,165,522 | 2,739,971 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
KENNEWICK | 646,449 | 23.6% |
WSDOT Funding | 0 | 0.0% |
STP | 928,000 | 33.7% |
Total Local Funding | 1,574,449 | 0.0% |
Project Description
This project will reconstruct the existing roadway to include four travel lanes, a center left-turn lane, bicycle lanes, curb and gutter, and sidewalks. Included in the project will be modification of the traffic signals at both ends.
Existing Condition
Project Benefits
- Improves safety;
- Completes corridor;
- Reduces congestion
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
Schedule Issues Level 1 Board Delay |
10/27/2015 |