The existing street is located in the heart of the Whitworth University campus. The pavement is cracked, patched, and rutted. Nearly 2,600 students cross the street to access campus facilities on both sides of Hawthorne. Sidewalk exists on both sides of the three-lane section however, Whitworth officials are concerned about pedestrian safety at the crosswalks. The university offered to maintain any landscaping added to improve safety at the crossings.
TIB Project Information
Spokane County's Hawthorne Road
8-3-032(069)-1
8-3-032(069)-1
Hawthorne Road
Waikiki Road to Division Street (SR 395)
FY 2017 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $768,654
County: Spokane | Legislative District: 7 | Project Length: 0.59 | TIB Engineer: Andrew Beagle | Last Payment Date: 07/05/2019
Project Information
Lead Agency | SPOKANE COUNTY |
Funding Year | 2017 |
Program | UAP |
Current Phase | Audit |
Legislative District | 7, 6 |
Congressional District | 5 |
Federal Route Number | 3974 |
Project Length | 0.59 mi. |
ADT | 10,397 |
Functional Class | Minor |
Type of Work | Reconstruction |
Project Contact | Tim Schwab |
Contact Email | TSCHWAB@spokanecounty.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 07/05/2019 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2015 | |
Delayed Project Date | 07/01/2020 | |
DAHP Assessment Date | 02/09/2016 | |
Predesign Approval | ||
Design Approval | 01/15/2016 | 01/20/2016 |
Bid Auth. Approval | 04/01/2016 | 03/30/2016 |
Construction Approval | 05/01/2016 | 05/03/2016 |
Project Closeout | 06/01/2019 | 06/20/2019 |
Audit Date | 07/05/2019 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 69,971 | 136,297 |
Right of Way | 0 | 0 |
Total Design | 69,971 | 136,297 |
Construction Engineering | 46,647 | 123,183 |
Construction Contract | 545,777 | 1,247,239 |
Other Construction | 6,000 | 0 |
Total Construction | 598,424 | 1,370,422 |
Funding Increase | 100,259 | |
Total TIB Funding | 768,654 | 1,506,719 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SPOKANE COUNTY | 258,673 | 17.2% |
WSDOT Funding | 0 | 0.0% |
WA State DOE | 479,392 | 31.8% |
Total Local Funding | 738,065 | 49.0% |
Project Description
The county originally proposed full depth reclamation with cement treated base. Constructability of an FDR section is compromised because of meandering medians and swales. The section is Landscaped median and swales provide stormwater collection and treatment. Center turn lanes at intersections allow for uninterrupted traffic flow. The landscaped median improves the corridor aesthetics and provides pedestrian refuge. The scope includes upgrade of all non-compliant ADA ramps.
Existing Condition
Project Benefits
- Extends improvements;
- Restores structural condition;
- Incorporates recycled materials
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |