228th Street SW currently does not exist between SR 99 and 76th Ave W and the skewed intersection of SR 99 and 76th Ave W has a significant crash history.
TIB Project Information
City of Edmonds's 228th Street SW/SR 99
8-1-139(002)-1
8-1-139(002)-1
228th Street SW/SR 99
80th Ave to 1,000 e/o 72nd/228th St SW to 76th Ave
FY 2015 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $1,365,638
County: Snohomish | Legislative District: 21 | Project Length: 0.90 | TIB Engineer: Greg Armstrong | Last Payment Date: 04/16/2018
Project Information
Lead Agency | EDMONDS |
Funding Year | 2015 |
Program | UAP |
Current Phase | Audit |
Legislative District | 21, 32 |
Congressional District | 2, 7 |
Federal Route Number | 0099 |
Project Length | 0.90 mi. |
ADT | 3,400 |
Functional Class | Principal |
Type of Work | Safety |
Project Contact | Bertrand Hauss |
Contact Email | bertrand.hauss@edmondswa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 04/16/2018 |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2013 | |
Delayed Project Date | 07/01/2018 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/15/2014 | 02/10/2014 |
Bid Auth. Approval | 02/17/2015 | 02/19/2015 |
Construction Approval | 04/24/2015 | 04/27/2015 |
Project Closeout | 05/01/2018 | 04/10/2018 |
Audit Date | 04/16/2018 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 247,000 | 851,827 |
Construction Contract | 1,475,000 | 5,166,492 |
Other Construction | 0 | 62,253 |
Total Construction | 1,722,000 | 6,080,572 |
Funding Surplus | - 356,362 | |
Total TIB Funding | 1,365,638 | 6,080,572 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
EDMONDS | 364,868 | 6.0% |
WSDOT Funding | 592,943 | 9.8% |
HSIP | 3,460,008 | 56.9% |
Mountlake Terrace | 297,115 | 4.9% |
Total Local Funding | 4,714,934 | 77.6% |
Project Description
This project constructs the missing segment of 228th Street SW between SR 99 and 76th Avenue W and a new signal will be added at SR 99. The intersection of 76th Ave W and SR 99 will be reconfigured to eliminate left turn movement and a center median will be added on SR 99 to restrict access. In addition, bike lanes, sidewalks and illumination will be added to both sides of 228th Street and the storm water systems will be improved using detention vault, infiltration galleries and a bio-swale.
Existing Condition
Project Benefits
- Improves safety;
- Completes missing link;
- Provides access control
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |