TIB Project Information

City of SeaTac's 28th/24th Avenue S

8-1-121(007)-1

8-1-121(007)-1
28th/24th Avenue S

S 200th St to S 208th St

FY 2015 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $4,902,163

County: King   |   Legislative District: 33   |   Project Length: 0.53   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 11/01/2018

Project Information

Lead Agency SEATAC
Funding Year 2015
Program UAP
Current Phase Audit
Legislative District 33
Congressional District 9
Federal Route Number 1231
Project Length 0.53 mi.
ADT 0
Functional Class Principal
Type of Work New Location
Project Contact Florendo Cabudol
Contact Email fcabudol@ci.seatac.wa.us
TIB Engineer Greg Armstrong
Last Payment Date 11/01/2018
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2013
Delayed Project Date 07/01/2018  
DAHP Assessment Date   09/24/2013
Predesign Approval
Design Approval 02/28/2014 02/20/2014
Bid Auth. Approval 03/10/2016 03/02/2016
Construction Approval 04/19/2016 04/19/2016
Project Closeout 10/15/2018 10/16/2018
Audit Date   11/01/2018
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 2,876,369
Right of Way 1,320,000 5,608,512
Total Design 1,320,000 8,484,881
     
Construction Engineering 410,500 2,063,673
Construction Contract 5,069,500 13,186,368
Other Construction 0 522,923
Total Construction 5,480,000 15,772,964
     
Funding Increase 333,536  
Funding Surplus - 2,231,373  
Total TIB Funding 4,902,163 24,257,845

Local Funding Partners

Funding Amount Percent
SEATAC 8,126,482 33.5%
WSDOT Funding 0 0.0%
FMSIB  2,500,000 11.3%
Sound Transit  3,400,000 15.4%
Leg Funding Package  5,329,200 22.0%
 
 
 
 
 
Total Local Funding 19,355,682 82.2%

Project Description

This project constructs a new roadway linking S 200th Street to S 208th Street. The project will include four travel lanes, a landscaped median with turn pockets, curb, gutter, shared-use path for bicycles and pedestrians, low impact development storm water collection and treatment facilities, retaining walls, channelization, landscaping and underground utilities.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments