TIB Project Information

City of Leavenworth's Commercial Street

6-E-850(010)-1

6-E-850(010)-1
Commercial Street

3rd St to 8th St

FY 2015 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $607,662

County: Chelan   |   Legislative District: 12   |   Project Length: 0.31   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 08/10/2017

Project Information

Lead Agency LEAVENWORTH
Funding Year 2015
Program SCAP
Current Phase Audit
Legislative District 12
Congressional District 8
Federal Route Number 04LD
Project Length 0.31 mi.
ADT 800
Functional Class Collector
Type of Work Reconstruction
Project Contact Joel Walinski
Contact Email cityadministrator@cityofleavenworth.com
TIB Engineer Andrew Beagle
Last Payment Date 08/10/2017
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2013
Delayed Project Date 07/01/2016  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2014 02/05/2014
Bid Auth. Approval 02/01/2015 02/26/2015
Construction Approval 03/23/2015 03/31/2015
Project Closeout 02/01/2017 08/03/2017
Audit Date   08/10/2017
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 49,167
Right of Way 0 0
Total Design 0 49,167
     
Construction Engineering 88,795 142,201
Construction Contract 592,830 1,112,614
Other Construction 0 18,930
Total Construction 681,625 1,273,745
     
Funding Increase 22,401  
Funding Surplus - 96,364  
Total TIB Funding 607,662 1,322,912

Local Funding Partners

Funding Amount Percent
LEAVENWORTH 97,207 7.3%
WSDOT Funding 0 0.0%
STP Funding  618,043 46.7%
 
 
 
 
 
 
 
Total Local Funding 715,250 54.0%

Project Description

The project reconstructs the roadway to provide two travel lanes and sidewalk on one side. A retaining wall will be built to allow for the wider section. The project also includes an illumination system and drainage improvements.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments