The existing intersection of Sleater Kinney Road and 6th Avenue SE is currently signalized with a 100 foot offset between the east and the west legs.
TIB Project Information
City of Lacey's Sleater Kinney Road SE
8-5-197(021)-1
8-5-197(021)-1
Sleater Kinney Road SE
Sleater Kinney Rd to 450' east on 6th Ave
FY 2002 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $816,811
County: Thurston | Legislative District: 22 | Project Length: 0.09 | TIB Engineer: Chris Langhoff | Last Payment Date: 10/27/2009
Project Information
Lead Agency | LACEY |
Funding Year | 2002 |
Program | UAP |
Current Phase | Audit |
Legislative District | 22 |
Congressional District | 10 |
Federal Route Number | 5265 |
Project Length | 0.09 mi. |
ADT | 27,334 |
Functional Class | Principal |
Type of Work | New Location |
Project Contact | Martin Hoppe |
Contact Email | mhoppe@ci.lacey.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 10/27/2009 |
Cultural Resource Assessment |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 01/26/2001 | |
Delayed Project Date | 07/01/2005 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 08/01/2001 | 09/25/2001 |
Bid Auth. Approval | 09/30/2007 | 09/19/2007 |
Construction Approval | 11/01/2007 | 10/29/2007 |
Project Closeout | 12/15/2009 | 10/20/2009 |
Audit Date | 10/27/2009 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 9,000 | 0 |
Design | 92,400 | 182,789 |
Right of Way | 195,000 | 761,714 |
Total Design | 308,400 | 964,503 |
Construction Engineering | 56,471 | 128,041 |
Construction Contract | 451,940 | 924,068 |
Other Construction | 0 | 13,915 |
Total Construction | 508,411 | 1,066,024 |
Total TIB Funding | 816,811 | 2,030,527 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LACEY | 393,785 | 19.4% |
WSDOT Funding | 0 | 0.0% |
Traffic Mitigation | 303,788 | 15.0% |
STP Funds | 516,143 | 25.4% |
Total Local Funding | 1,213,716 | 59.3% |
Project Description
This project will realign the east leg of 6th Avenue SE 100 feet to the south. The existing traffic signal will be removed and a new signal will be installed at the realigned intersection. Included in the project will be sidewalks, curbs and gutter, illumination, and landscaping.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
Right Of Way Issues Level 3 Board Delay |
10/29/2007 | City attempted to obtain ROW from Office Depot to enable realignment of 6th Avenue the court sided with Office Depot and denied the request. The city has been given until January 2007 to present a revised scope to the Board. |