Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Arlington's Complete Streets Award

C-P-817(001)-1

C-P-817(001)-1
Complete Streets Award

March 2019 Selection

FY 2020 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $605,000

County: Snohomish   |   Legislative District: 39   |   Project Length: 0.10   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 02/26/2020

Project Information

Lead Agency ARLINGTON
Funding Year 2020
Program CSP
Current Phase Audit
Legislative District 39
Congressional District 2
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Pedestrian
Project Contact Nova Heaton
Contact Email nheaton@arlingtonwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 02/26/2020
Cultural Resource Assessment

Project Schedule

  Target Date Actual Date
Project Selection Date   03/22/2019
Delayed Project Date 07/01/2021  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/01/2019
Bid Auth. Approval 05/01/2019
Construction Approval 05/01/2019 04/23/2019
Project Closeout 03/15/2022 03/17/2022
Audit Date   03/17/2022
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 605,000 605,000
Other Construction 0 0
Total Construction 605,000 605,000
     
Total TIB Funding 605,000 605,000

Local Funding Partners

Funding Amount Percent
ARLINGTON 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Complete Streets Workplan

Item Type of Work Date Added Est. Cost Actual Cost Complete
188th Street Sidewalk Pedestrian Mar 2019 $130,000 $130,000
Install 600 lf of curb,gutter and sidewalk along the south side of 188th Street NE adjacent to two city parks and sports fields. Including a planter strip, low impact drainage improvements and street trees
59th Ave NE Sidewalk Pedestrian Mar 2019 $262,000 $262,000
Install 750 lf of curb, gutter and sidewalk along the east side of 59th Ave NE adjacent to Bill Quake Park and sports fields. Including a planer strip, low impact drainage improvements and street trees.
Public Art Installation and Decorative Bike Rack Bicycle; Aesthetics Mar 2019 $12,000 $12,000
Commission and install public art at the corner of 59th Ave and 188th Street to celebrate the youth sports activity in the area. Install decorative bike racks at city parks.
Mid-Block Crossing on 188th St NE Pedestrian Mar 2019 $18,000 $18,000
Install a Rectangular Rapid Flashing Beacon, crosswalk, and ADA ramps between parking areas for three adjacent parks and a proposed future transit stop.
Mid-Block Crossing on 59th Ave NE Pedestrian Mar 2019 $18,000 $18,000
Install a Rectangular Rapid Flashing Beacon, crosswalk, and ADA ramps to connect existing Airport Trail to Boys and Girl Club, parks and sports fields.
Evans Park Sidewalk Pedestrian Mar 2019 $160,000 $160,000
Install 450 lf of shoulder, curb, gutter and sidewalk along the east side of 59th Ave NE adjacent to Evans Park
Complete Streets Leadership Academy Feb 2020 $5,000 $5,000
Training and demostration project

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments