City of Yakima's Nob Hill Boulevard Overlay

8-4-180(026)-1

8-4-180(026)-1
Nob Hill Boulevard Overlay

S 15th Ave to S 28th Ave

FY 2024 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,337,216

County: Yakima   |   Legislative District: 14   |   Project Length: 0.85   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 12/04/2023

Project Information

Lead Agency YAKIMA
Funding Year 2024
Program UAP
Current Phase Construction
Legislative District 14, 15
Congressional District 4
Federal Route Number 4566
Project Length 0.85 mi.
ADT 21,615
Functional Class Principal
Type of Work Resurfacing
Project Contact Bill Preston
Contact Email bill.preston@yakimawa.gov
TIB Engineer Jonathan Heusman
Last Payment Date 12/04/2023
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 01/01/2024  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 02/17/2023
Bid Auth. Approval 04/30/2023 04/04/2023
Construction Approval 05/01/2023 05/16/2023
Project Closeout 03/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 127,880 209,640
Construction Contract 1,207,120 1,486,880
Other Construction 0 0
Total Construction 1,335,000 1,696,520
     
Funding Increase 2,216  
Total TIB Funding 1,337,216 1,696,520

Local Funding Partners

Funding Amount Percent
YAKIMA 359,304 21.2%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 359,304 21.2%

Project Description

The proposed improvements consist of milling and overlaying the existing asphalt, crack sealing, new pavement markings, and replacement of non-ADA compliant curb ramps. Improvements include spot pavement repair areas where pavement has completely failed in isolated locations.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments