Bill # Payment Date Type Predesign Spec. Study DE Engr. Right of Way CN Engr. CN Other CN Contract Total
1 10/03/2023 Payment 0.00 0.00 0.00 0.00 0.00 0.00 546,978.57 546,978.57
2 11/13/2023 Payment 0.00 0.00 0.00 0.00 0.00 0.00 560,765.32 560,765.32
3 12/04/2023 Payment 0.00 0.00 0.00 0.00 0.00 0.00 22,149.47 22,149.47
TOTAL PAYMENTS 0.00 0.00 0.00 0.00 0.00 0.00 1,129,893.36 1,129,893.36