Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Yakima's N 1st Street

8-4-180(025)-1

8-4-180(025)-1
N 1st Street

MLK Blvd to J St

FY 2023 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,500,000

County: Yakima   |   Legislative District: 14   |   Project Length: 0.75   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 03/25/2024

Project Information

Lead Agency YAKIMA
Funding Year 2023
Program UAP
Current Phase Construction
Legislative District 14, 15
Congressional District 4
Federal Route Number 4579
Project Length 0.75 mi.
ADT 20,880
Functional Class Principal
Type of Work Major Widening
Project Contact Bill Preston
Contact Email Bill.Preston@yakimawa.gov
TIB Engineer Jonathan Heusman
Last Payment Date 03/25/2024
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 01/01/2023  
DAHP Assessment Date   03/15/2022
Predesign Approval
Design Approval 04/01/2022 03/02/2022
Bid Auth. Approval 04/30/2023 04/21/2023
Construction Approval 08/24/2023 08/29/2023
Project Closeout 06/30/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 155,936 1,573,160
Construction Contract 1,199,464 9,022,883
Other Construction 144,600 782,622
Total Construction 1,500,000 11,378,665
     
Total TIB Funding 1,500,000 11,378,665

Local Funding Partners

Funding Amount Percent
YAKIMA 4,878,665 42.9%
WSDOT Funding 0 0.0%
NHFP  2,090,000 19.6%
NHPP  2,910,000 25.6%
 
 
 
 
 
 
Total Local Funding 9,878,665 88.1%

Project Description

Reconstruction of N. 1st St. from MLK Boulevard to 'J' Street. The project will include curb and gutter, sidewalks, ADA-compliant curb ramps at all intersections, storm drainage facilities, illumination system, pedestrian lighting, two traffic signals, in-ground planters with street trees, on-street parking removal, add bike lanes and domestic water main replacement.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments