The current road base is concrete pavement covered with multiple asphalt overlays. N. 1st St. is a WSDOT T-3 Truck Freight Corridor, with an average of 1,310 commercial trucks per day. The roadway surface condition is poor with longitudinal, transverse, alligator cracking, rutting, and spalling along the corridor. The most severe cracks are at locations of underlying concrete panel joints. The curb and gutter, sidewalks, and curb ramps, along both sides are also deficient. Additionally, the water mains under the roadway are 50 to 75 years old and will be replaced.
Projects — TIB Project Information
TIB Project Information
City of Yakima's N 1st Street
8-4-180(025)-1
8-4-180(025)-1
N 1st Street
MLK Blvd to J St
FY 2023 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,500,000
County: Yakima | Legislative District: 14 | Project Length: 0.75 | TIB Engineer: Jonathan Heusman | Last Payment Date: 10/29/2024
Project Information
Lead Agency | YAKIMA |
Funding Year | 2023 |
Program | UAP |
Current Phase | Construction |
Legislative District | 14, 15 |
Congressional District | 4 |
Federal Route Number | 4579 |
Project Length | 0.75 mi. |
ADT | 20,880 |
Functional Class | Principal |
Type of Work | Major Widening |
Project Contact | Bill Preston |
Contact Email | Bill.Preston@yakimawa.gov |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 10/29/2024 |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 01/01/2023 | |
DAHP Assessment Date | 03/15/2022 | |
Predesign Approval | ||
Design Approval | 04/01/2022 | 03/02/2022 |
Bid Auth. Approval | 04/30/2023 | 04/21/2023 |
Construction Approval | 08/24/2023 | 08/29/2023 |
Project Closeout | 06/30/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 155,936 | 1,573,160 |
Construction Contract | 1,199,464 | 9,022,883 |
Other Construction | 144,600 | 782,622 |
Total Construction | 1,500,000 | 11,378,665 |
Total TIB Funding | 1,500,000 | 11,378,665 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
YAKIMA | 4,878,665 | 42.9% |
WSDOT Funding | 0 | 0.0% |
NHFP | 2,090,000 | 19.6% |
NHPP | 2,910,000 | 25.6% |
Total Local Funding | 9,878,665 | 88.1% |
Project Description
Reconstruction of N. 1st St. from MLK Boulevard to 'J' Street. The project will include curb and gutter, sidewalks, ADA-compliant curb ramps at all intersections, storm drainage facilities, illumination system, pedestrian lighting, two traffic signals, in-ground planters with street trees, on-street parking removal, add bike lanes and domestic water main replacement.
Existing Condition
Project Benefits
- Pedestrian safety will improve through new wide, amenity-zone sidewalks, pedestrian level lighting, and ADA curb ramps. Energy efficient lighting will improve safety for motorists, pedestrians, and bicyclists in addition to saving on electricity costs. Bike lanes will safely accommodate a growing bicycle community. Additionally, completion of this project will bring new businesses to this area filling vacant buildings, increasing jobs, and commerce.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |