City of Richland's Duportail Bridge
8-4-171(019)-1
8-4-171(019)-1
Duportail Bridge
City View Dr to Riverstone Dr
FY 2018 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $9,000,000
County: Benton | Legislative District: 8 | Project Length: 0.50 | TIB Engineer: Jonathan Heusman | Last Payment Date: 08/16/2021
Project Information
Lead Agency | RICHLAND |
Funding Year | 2018 |
Program | UAP |
Current Phase | Audit |
Legislative District | 8 |
Congressional District | 4 |
Federal Route Number | 3440 |
Project Length | 0.50 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Bridge |
Project Contact | Pete Rogalsky |
Contact Email | progalsky@ci.richland.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 08/16/2021 |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 06/21/2017 | |
Delayed Project Date | 07/01/2021 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 07/01/2017 | 05/22/2017 |
Bid Auth. Approval | 09/01/2017 | 10/16/2017 |
Construction Approval | 11/30/2017 | 01/09/2018 |
Project Closeout | 07/30/2021 | 08/10/2021 |
Audit Date | 08/16/2021 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 685,000 | 639,688 |
Right of Way | 172,000 | 156,401 |
Total Design | 857,000 | 796,089 |
Construction Engineering | 0 | 1,324,585 |
Construction Contract | 8,143,000 | 21,428,170 |
Other Construction | 0 | 97,084 |
Total Construction | 8,143,000 | 22,849,839 |
Total TIB Funding | 9,000,000 | 23,645,928 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
RICHLAND | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Federal Funds | 1,008,980 | 4.1% |
Connecting Washington | 13,636,948 | 57.7% |
Total Local Funding | 14,645,928 | 61.8% |
Project Description
The City’s plan to build the Duportail Bridge is firming up with each passing month. The Bridge will be the final segment in the Duportail / Stevens Corridor strategy to provide improved multi-modal connectivity between central Richland and the Queensgate area. The bridge will include two vehicle travel lanes in each direction, with bicycle lanes and sidewalks on each side. Tanglewood Drive will connect Duportail Street to the residential developments to the north and the south. The intersection of Duportail Street and Tanglewood Drive will be controlled by a traffic signal. The intersection of Duportail Street and SR240 will be widened and improved, as will the at-grade railroad crossing on the Port of Benton Railroad. The project will also replace a water supply pipeline, currently located in the Yakima River, with two bridge-mounted pipelines.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |