Bill # Payment Date Type Predesign Spec. Study DE Engr. Right of Way CN Engr. CN Other CN Contract Total
1 11/15/2017 Payment 0.00 0.00 383,114.69 15,355.42 0.00 0.00 0.00 398,470.11
2 01/16/2018 Payment 0.00 0.00 314,153.17 30,170.91 0.00 1,879.79 0.00 346,203.87
3 05/02/2018 Payment 0.00 0.00 568.09 0.00 25,270.77 75,944.50 36,413.99 138,197.35
4 06/20/2018 Payment 0.00 0.00 0.00 15,000.00 41,337.23 2,975.87 1,056,598.24 1,115,911.34
5 08/13/2018 Payment 0.00 0.00 0.00 0.00 60,082.11 0.00 1,358,060.15 1,418,142.26
6 09/12/2018 Payment 0.00 0.00 0.00 0.00 23,565.17 0.00 586,866.89 610,432.06
7 10/16/2018 Payment 0.00 0.00 0.00 0.00 23,876.57 0.00 66,021.32 89,897.89
8 11/13/2018 Payment 0.00 0.00 0.00 0.00 20,403.75 0.00 106,673.50 127,077.25
9 12/11/2018 Payment 0.00 0.00 0.00 0.00 47,659.18 1,037.53 394,410.96 443,107.67
10 01/17/2019 Payment 0.00 0.00 0.00 0.00 57,994.31 0.00 473,910.45 531,904.76
11 02/22/2019 Payment 0.00 0.00 0.00 0.00 19,730.07 0.00 381,649.33 401,379.40
12 03/27/2019 Payment 0.00 0.00 0.00 0.00 19,434.88 0.00 397,984.58 417,419.46
13 04/18/2019 Payment 0.00 0.00 0.00 0.00 10,531.80 0.00 438,580.65 449,112.45
14 05/15/2019 Payment 0.00 0.00 0.00 0.00 24,360.16 0.00 500,000.00 524,360.16
15 06/17/2019 Payment 0.00 0.00 0.00 0.00 0.00 0.00 312,306.91 312,306.91
16 07/16/2019 Payment 0.00 0.00 0.00 0.00 17,208.78 0.00 314,689.76 331,898.54
17 08/28/2019 Payment 0.00 0.00 0.00 0.00 15,975.22 3,241.66 614,249.16 633,466.04
18 09/24/2019 Payment 0.00 0.00 0.00 0.00 11,281.20 3,404.33 246,026.95 260,712.48
19 08/16/2021 Audit 0.00 0.00 -454,361.10 -997.76 85,445.72 -51,532.05 871,445.19 450,000.00
TOTAL PAYMENTS 0.00 0.00 243,474.85 59,528.57 504,156.92 36,951.63 8,155,888.03 9,000,000.00