12th Street is a north/south connector street that provides access to downtown to the south and residential neighborhood to the north. The existing street surface is alligatored and cracking with areas of rutting and missing pavement. The east side of the roadway has curb, gutter, sidewalk and closed system drainage and is proposed to be retained. Three existing ADA ramps within the project limits do not meet current ADA requirements and will be updated. As there is limited storm drainage on the west side causing runoff to flow on to private property during heavy rainfall events, closed system drainage will be added to the west side and directed to a treatment and infiltration swale at the NW corner of 12th and Wakefield.
Projects — TIB Project Information
TIB Project Information
City of Elma's 12th Street Improvements
6-W-955(012)-1
6-W-955(012)-1
12th Street Improvements
Wakefield Ave to Harding St
FY 2022 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $414,891
County: Grays Harbor | Legislative District: 24 | Project Length: 0.13 | TIB Engineer: Chris Langhoff | Last Payment Date: 08/23/2021
Project Information
Lead Agency | ELMA |
Funding Year | 2022 |
Program | SCAP |
Current Phase | Construction |
Legislative District | 24 |
Congressional District | 6 |
Federal Route Number | 9999 |
Project Length | 0.13 mi. |
ADT | 1,500 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Jim Starks |
Contact Email | jim@cityofelma.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 08/23/2021 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2020 | |
Delayed Project Date | 07/01/2023 | |
Predesign Approval | ||
Design Approval | 02/01/2021 | 12/29/2020 |
Bid Auth. Approval | 05/01/2022 | 02/10/2022 |
Construction Approval | 04/01/2022 | 03/28/2022 |
Project Closeout | 02/28/2023 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 47,864 | 66,000 |
Right of Way | 0 | 0 |
Total Design | 47,864 | 66,000 |
Construction Engineering | 47,864 | 73,500 |
Construction Contract | 319,163 | 490,000 |
Other Construction | 0 | 0 |
Total Construction | 367,027 | 563,500 |
Total TIB Funding | 414,891 | 629,500 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ELMA | 214,609 | 34.1% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 214,609 | 34.1% |
Project Description
Reconstruct the existing roadway surface, while retaining the existing curb, gutter, sidewalk and storm drainage on the east side. Install curb, gutter and closed system drainage and on the west side to keep roadway runoff from flowing on to private property, and discharge collected runoff to a treatment and infiltration swale at the NW corner of 12th and Wakefield.
Existing Condition
Project Benefits
- Improves arterial network;
- Restores structural condition;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |