The existing street is showing signs of surface and subgrade failure. There are not any pedestrian facilities and the existing illumination is inadequate. This project connects two arterials in the Town, Spring Street and Guard Street. The Town completed improvements on Marguerite between Park Street and Guard Street in 2020.
Projects — TIB Project Information
TIB Project Information
Town of Friday Harbor's Marguerite Place
6-W-831(010)-1
6-W-831(010)-1
Marguerite Place
Spring St to Park St
FY 2023 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $925,000
County: San Juan | Legislative District: 40 | Project Length: 0.24 | TIB Engineer: Chris Langhoff | Last Payment Date: 04/25/2024
Project Information
Lead Agency | FRIDAY HARBOR |
Funding Year | 2023 |
Program | SCAP |
Current Phase | Construction |
Legislative District | 40 |
Congressional District | 2 |
Federal Route Number | 9999 |
Project Length | 0.24 mi. |
ADT | 2,470 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Denice Kulseth |
Contact Email | dkulseth@fridayharbor.org |
TIB Engineer | Chris Langhoff |
Last Payment Date | 04/25/2024 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | 05/20/2022 | |
Predesign Approval | ||
Design Approval | 03/01/2022 | 03/08/2022 |
Bid Auth. Approval | 05/01/2024 | 05/22/2024 |
Construction Approval | 06/12/2024 | 06/14/2024 |
Project Closeout | 12/01/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 91,128 | 178,305 |
Right of Way | 10,222 | 0 |
Total Design | 101,350 | 178,305 |
Construction Engineering | 91,128 | 178,305 |
Construction Contract | 607,522 | 1,841,789 |
Other Construction | 0 | 0 |
Total Construction | 698,650 | 2,020,094 |
Funding Increase | 125,000 | |
Total TIB Funding | 925,000 | 2,198,399 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
FRIDAY HARBOR | 1,273,399 | 57.9% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 1,273,399 | 57.9% |
Project Description
This project will provide an accessible pedestrian connection between residential neighborhoods, daycare, pre-schools, private schools, library, the high school, a church, a baseball park, and professional services. By reconstructing the street and installing sidewalks and illumination the Town will provide a safe and efficient route for motorists and pedestrians.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Improves arterial network;
- Improves mobility;
- Restores structural condition
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |