Stanley Street is a major arterial through the City and provides direct access to both residential and commercial properties. Stanley Street is also the most direct route to both enter and leave the City. Intersection control along Stanley Street includes a traffic signal at Jordan Road and the all-way stop at Granite Avenue. All other minor intersections are stop controlled on the minor street. Due to the significant traffic volumes (the City is scheduled to complete traffic counts in late 2021) on Stanley Street, heavy congestion occurs during the morning and evening commute on the various minor streets. Galena Street, which parallels Stanley Street and is located one block south of Stanley Street, terminates at Portage Avenue. Traffic on Galena Street then uses Portage Avenue to access Stanley Street, which can be difficult when traffic volumes are high.
Projects — TIB Project Information
TIB Project Information
City of Granite Falls's Galena Street Extension
6-P-820(010)-1
6-P-820(010)-1
Galena Street Extension
Stanley St to Portage Ave
FY 2023 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $723,212
County: Snohomish | Legislative District: 39 | Project Length: 0.23 | TIB Engineer: Greg Armstrong | Last Payment Date: 08/14/2024
Project Information
Lead Agency | GRANITE FALLS |
Funding Year | 2023 |
Program | SCAP |
Current Phase | Audit |
Legislative District | 39 |
Congressional District | 1 |
Federal Route Number | 9999 |
Project Length | 0.23 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | New Location |
Project Contact | Brent Kirk |
Contact Email | brent.kirk@ci.granite-falls.wa.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | 08/14/2024 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 01/01/2023 | |
DAHP Assessment Date | 08/27/2021 | |
Predesign Approval | ||
Design Approval | 02/01/2022 | 12/06/2021 |
Bid Auth. Approval | 04/21/2023 | 04/13/2023 |
Construction Approval | 05/11/2023 | 05/18/2023 |
Project Closeout | 08/31/2024 | 08/13/2024 |
Audit Date | 08/14/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 78,261 | 85,000 |
Construction Contract | 521,739 | 2,308,370 |
Other Construction | 0 | 0 |
Total Construction | 600,000 | 2,393,370 |
Funding Increase | 123,212 | |
Total TIB Funding | 723,212 | 2,393,370 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GRANITE FALLS | 1,670,158 | 69.8% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 1,670,158 | 69.8% |
Project Description
This project will extend Galena Street to the west and north, ultimately connecting to the existing signalized intersection at Stanley St and Jordan Rd. This extension will allow traffic on Galena Street the opportunity to access Stanley St at a traffic signal at Jordan Rd versus the stopped controlled intersection at Portage Ave.
Existing Condition
Project Benefits
- Improves arterial network;
- Completes gap;
- Improves vehicle and pedestrian access
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |