Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Town of Winthrop's Horizon Flats Road

6-E-887(006)-1

6-E-887(006)-1
Horizon Flats Road

Twin Lakes Rd to 3650 feet south

FY 2023 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $961,136

County: Okanogan   |   Legislative District: 12   |   Project Length: 0.69   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 01/29/2024

Project Information

Lead Agency WINTHROP
Funding Year 2023
Program SCAP
Current Phase Design
Legislative District 12
Congressional District 4
Federal Route Number 9999
Project Length 0.69 mi.
ADT 1,200
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Pete Cowger
Contact Email pcowger@varela-engr.com
TIB Engineer Andrew Beagle
Last Payment Date 01/29/2024
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2024  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2022 01/25/2022
Bid Auth. Approval 02/15/2024
Construction Approval 04/01/2024
Project Closeout 09/15/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 113,520 119,495
Right of Way 0 0
Total Design 113,520 119,495
     
Construction Engineering 90,816 95,596
Construction Contract 756,800 796,632
Other Construction 0 0
Total Construction 847,616 892,228
     
Total TIB Funding 961,136 1,011,723

Local Funding Partners

Funding Amount Percent
WINTHROP 50,587 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 50,587 5.0%

Project Description

***Updated Scope Approved 5/19/2023 Board Action*** Three distinct sections and revised drainage solution. Stormwater will be collected with catch basins and conveyed to drywells. Additional capacity for overflow will occur at a recently constructed swale near the new fire station (mid section vicinity). The intent is to avoid slope erosion particularly on the upper section where 21 side slopes exist. The pavement scope is different for each section Lower section - Twin Lakes Road to 1000 feet south (first curve vicinity) - pulverize existing asphalt, regrade roadway crown, 5” crushed surfacing top course (CSTC), and overlay with 3.5” of Hot Mix Asphalt (HMA). Mid section - between curves – install 12” perf pipe from catch basins to a down gradient drywell and existing swale adjacent to the fire department property. Full depth shoulder widening and 0.15’ full section HMA overlay. Upper section – Second Curve vicinity to project limit – Widen shoulders with 4” CSTC and 1.25” HMA. 0.15’ full section HMA overlay.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments