The pavement condition rating of SE 256th Street - 148th Ave SE to 156th Ave SE 50.
Projects — TIB Project Information
TIB Project Information
City of Covington's SE 256th Street Overlay
3-P-204(007)-1
3-P-204(007)-1
SE 256th Street Overlay
148th Ave SE to 156th Ave SE
FY 2024 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $437,576
County: King | Legislative District: 47 | Project Length: 0.51 | TIB Engineer: Greg Armstrong | Last Payment Date: 01/02/2024
Project Information
Lead Agency | COVINGTON |
Funding Year | 2024 |
Program | APP |
Current Phase | Audit |
Legislative District | 47 |
Congressional District | 8 |
Federal Route Number | 1170 |
Project Length | 0.51 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Resurfacing |
Project Contact | Bob Lindskov |
Contact Email | Blindskov@covingtonwa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 01/02/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/28/2023 | 02/09/2023 |
Bid Auth. Approval | 06/01/2023 | 05/25/2023 |
Construction Approval | 06/27/2023 | 06/29/2023 |
Project Closeout | 12/31/2023 | 12/14/2023 |
Audit Date | 01/02/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 79,943 | 94,050 |
Right of Way | 0 | 0 |
Total Design | 79,943 | 94,050 |
Construction Engineering | 79,943 | 29,817 |
Construction Contract | 532,950 | 452,751 |
Other Construction | 0 | 0 |
Total Construction | 612,893 | 482,568 |
Funding Surplus | - 255,260 | |
Total TIB Funding | 437,576 | 576,618 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
COVINGTON | 139,609 | 24.4% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 139,609 | 24.4% |
Project Description
This project grinds and provides a 2 inch overlay of SE 256th Street - 148th Ave SE to 156th Ave SE and upgrades 2 ADA ramps
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |