The pavement condition rating of N Levee Road between 70th Ave E and Freeman Rd E 50.
Projects — TIB Project Information
TIB Project Information
City of Fife's N Levee Road Overlay
3-P-134(001)-1
3-P-134(001)-1
N Levee Road Overlay
70th Ave E to Freeman Rd E
FY 2024 Arterial Preservation Program
Current Phase : Closeout
Total TIB Funding : $508,292
County: Pierce | Legislative District: 25 | Project Length: 0.82 | TIB Engineer: Greg Armstrong | Last Payment Date: 12/02/2024
Project Information
Lead Agency | FIFE |
Funding Year | 2024 |
Program | APP |
Current Phase | Closeout |
Legislative District | 25 |
Congressional District | 10 |
Federal Route Number | 3216 |
Project Length | 0.82 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Greg Vigoren |
Contact Email | gvigoren@cityoffife.org |
TIB Engineer | Greg Armstrong |
Last Payment Date | 12/02/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 01/11/2023 |
Bid Auth. Approval | 03/31/2024 | 02/08/2024 |
Construction Approval | 03/19/2024 | 03/21/2024 |
Project Closeout | 11/30/2024 | 11/20/2024 |
Audit Date | 12/02/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 118,761 | 82,320 |
Right of Way | 0 | 0 |
Total Design | 118,761 | 82,320 |
Construction Engineering | 118,761 | 60,351 |
Construction Contract | 791,743 | 459,747 |
Other Construction | 0 | 500 |
Total Construction | 910,504 | 520,598 |
Funding Surplus | - 520,973 | |
Total TIB Funding | 508,292 | 602,918 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
FIFE | 94,626 | 15.7% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 94,626 | 15.7% |
Project Description
This project will include pavement repair, joint grinding, and overlaying the existing asphalt travel lanes and shoulders of N Levee Road between 70th Ave E and Freeman Rd E. All pavement markings and signing will be reinstalled to current MUTCD requirements.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |