Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of South Bend's Broadway Avenue Overlay

2-W-972(008)-1

2-W-972(008)-1
Broadway Avenue Overlay

Adams St to Monroe St

FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $192,930

County: Pacific   |   Legislative District: 19   |   Project Length: 0.26   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 01/16/2024

Project Information

Lead Agency SOUTH BEND
Funding Year 2024
Program SCPP
Current Phase Audit
Legislative District 19
Congressional District 3
Federal Route Number 9999
Project Length 0.26 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Dennis Houk
Contact Email dennis.houk@southbend-wa.gov
TIB Engineer Chris Langhoff
Last Payment Date 01/16/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 12/13/2022
Bid Auth. Approval 04/30/2023 04/19/2023
Construction Approval 05/30/2023 05/24/2023
Project Closeout 12/31/2023 01/09/2024
Audit Date   01/16/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 32,880 32,880
Right of Way 0 0
Total Design 32,880 32,880
     
Construction Engineering 32,880 12,897
Construction Contract 219,197 148,408
Other Construction 0 0
Total Construction 252,077 161,305
     
Funding Surplus - 92,027  
Total TIB Funding 192,930 194,185

Local Funding Partners

Funding Amount Percent
SOUTH BEND 1,255 0.6%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 1,255 0.6%

Project Description

2 inch overlay Broadway Avenue - Adams St to Monroe St

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments