Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Carnation's 2021 Overlay

2-P-801(003)-1

2-P-801(003)-1
2021 Overlay

Multiple Locations

FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $125,532

County: King   |   Legislative District: 5   |   Project Length: 0.27   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 04/15/2024

Project Information

Lead Agency CARNATION
Funding Year 2023
Program SCPP
Current Phase Audit
Legislative District 5
Congressional District 1
Federal Route Number 9999
Project Length 0.27 mi.
ADT 150
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Ana Cortez
Contact Email ana.cortez@carnationwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 04/15/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2024  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2022 12/02/2021
Bid Auth. Approval 03/15/2023 02/13/2023
Construction Approval 06/15/2023 06/22/2023
Project Closeout 06/30/2024 04/03/2024
Audit Date   04/15/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 25,150 0
Right of Way 0 0
Total Design 25,150 0
     
Construction Engineering 25,150 8,084
Construction Contract 125,760 134,218
Other Construction 0 0
Total Construction 150,910 142,302
     
Funding Increase 14,846  
Funding Surplus - 65,374  
Total TIB Funding 125,532 142,302

Local Funding Partners

Funding Amount Percent
CARNATION 16,770 11.8%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 16,770 11.8%

Project Description

Grind and 2-inch overlay of the following segments W Commercial - Tolt Ave to Stephens Ave 1 ADA Ramp W Bird - Tolt Ave to Stephens Ave - 1 ADA Ramp Myrtle Street - Tolt Ave to Stossel Ave

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments