Region: East | Legislative District: 7 | Length: 0.00 mi. | FY 2026 Small City Maintenance Program (SCMP) |
![]() |
Existing ConditionsWe have sections of roadway with significant cracking. |
Project Funding
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 0 | 0 | 0 |
Right of Way | 0 | 0 | 0 |
Construction | 11,091 | 584 | 11,675 |
Project Totals | $11,091 | $584 | $11,675 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
95.0% | 5.0% | 5% |
Summary of Improvements
Description of Improvements
We would like to crack seal as much as time allows next year, in preparation for chip seal in various locations during 2026-2027. We propose to rent a crack seal machine from Asphalt Supply for two weeks, and to purchase enough material to run the machine for those two weeks. Application will be handled by City staff. We will crack seal beginning with the worst sections and go until we run out of material, concentrating on 7th Street, Hospital Way and a few other isolated areas.