FY 2026 SCMP Selections

City of Medical Lake
2025 Street Maintenance
Multiple Locations
TIB Award Amount
$160,337
Region: East   |   Legislative District: 6   |   Length: 0.00 mi. FY 2026 Small City Maintenance Program (SCMP)

Existing Conditions

Before the county can start scrub sealing, all roads need maintenance. Scrub sealing will only address cracks up to 2 inches wide, but several roads, particularly in the Fox Hollow area north of SR902, have cracks between 3 and 4 inches. Many roads also have sections with spalled pavement or severe rutting that need repair.

Project Funding

  TIB Funds Local Funds Total Costs
Design 0 0 0
Right of Way 0 0 0
Construction 160,337 8,439 168,776
Project Totals $160,337 $8,439 $168,776

Local Match

TIB Participation Local Match Minimum Local Match
95.0% 5.0% 5%

Description of Improvements

The proposed solution involves several steps to prepare the roads for scrub sealing. Cracks between 3 and 4 inches will be filled with a polymer crack seal. For damaged areas, the plan includes removing the existing pavement and base, then installing 3 inches of hot mix asphalt (HMA) over a 6-inch layer of crushed surfacing top course (CSTC). Additionally, to address rutting and depressed sections, a skim coat of 3/8-inch HMA mix will be applied to ensure a smooth surface for the Countys scrub s