Region: East | Legislative District: 7 | Length: 0.30 mi. | FY 2025 Small City Arterial Program (SCAP) |
![]() |
Existing ConditionsThe existing roadway is deteriorating and does not have any storm drainage facilities or pedestrian facilities. PCR ranged from 50-54 (2023 Data). All parallel routes lack sidewalks, including SR 215. |
Project Funding
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 142,500 | 7,500 | 150,000 |
Right of Way | 0 | 0 | 0 |
Construction | 1,092,500 | 57,500 | 1,150,000 |
Project Totals | $1,235,000 | $65,000 | $1,300,000 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
95.0% | 5.0% | 5% |
Summary of Improvements
Description of Improvements
Reconstruct 3rd Avenue from Irene Street to Greta Street. Two 11-foot HMA lanes with rolled curb and gutter on both sides will be installed, with an 8-foot gravel parking lane serving as a buffer for a 5-foot sidewalk. Storm Drainage facilities will also be installed.