City of Grand Coulee
Spokane Way Improvements
Alcan Rd to E Grand Coulee Ave (SR 174)
TIB Award Amount
$126,875
Region: East   |   Legislative District: 7   |   Length: 0.19 mi. FY 2025 Small City Arterial Program (SCAP)

Existing Conditions

Spokane Way serves as the shortest route from the Towns of Hartline and Almira to Grand Coulee. The existing roadway has excessive steep banks, cross slopes, horizontal curves and pavement condition.

Project Funding

  TIB Funds Local Funds Total Costs
Design 13,913 97,387 111,300
Right of Way 6,250 43,750 50,000
Construction 106,713 746,987 853,700
Project Totals $126,875 $888,125 $1,015,000

Local Match

TIB Participation Local Match Minimum Local Match
12.5% 87.5% 0%

Description of Improvements

Reconstruct the roadway and realign. Cement treated base will likely be used and stormwater will be collected and conveyed to the existing system.