Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Funding Cycles

FY 2025 SCAP Selections

City of Millwood
Argonne Road Reconstruction - Phase 2
E Trent Ave to 150 ft s/o S Frederick Ave
TIB Award Amount
$1,409,230
Region: East   |   Legislative District: 4   |   Length: 0.22 mi. FY 2025 Small City Arterial Program (SCAP)

Existing Conditions

Argonne Road connects Spokane Valley and Millwood to north Spokane County areas, within the city the road is a primary means to access neighborhoods and business. ADT of 30,000+ with heavy peak hour congestion. Pavement, crossings and configuration are poor.

Project Funding

  TIB Funds Local Funds Total Costs
Design 129,865 6,835 136,700
Right of Way 0 0 0
Construction 1,279,365 67,335 1,346,700
Project Totals $1,409,230 $74,170 $1,483,400

Local Match

TIB Participation Local Match Minimum Local Match
95.0% 5.0% 5%

Description of Improvements

FDR with base stabilization (ATB or CTB) between Trent and about 150 feet south of Frederick. A HAWK signal at Buckeye. The existing sidewalk and curb on either side of the road will be maintained, but pedestrian ramps upgraded for compliance.