Region: East | Legislative District: 9 | Length: 0.42 mi. | FY 2026 Complete Streets Program (CSP) |
![]() |
Existing ConditionsW. Fir Street has been identified as a location with high pedestrian activity within the City of Connell that lacks pedestrian facilities yet contains nearly 200 homes and connects multiple public and private pedestrian generators. |
Project Funding
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 54,000 | 6,000 | 60,000 |
Right of Way | 0 | 0 | 0 |
Construction | 438,030 | 48,670 | 486,700 |
Project Totals | $492,030 | $54,670 | $546,700 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
90.0% | 10.0% | 5% |
Summary of Improvements
- The W. Fir Street Sidewalk Improvements Project will provide pedestrian accessibility to a quadrant of Connell that currently lacks pedestrian facilities. At present, no such facilities exist in an area housing a large portion of Connells population, and the area provides direct access to one of the Citys three parks. This project will promote pedestrian access for the residents adjacent to the project area and provide citywide access to Striker Park.
Description of Improvements
Install a cement concrete sidewalk, traffic curb and gutter as needed for ADA compliance, sidewalk ramps, and crosswalk lines along W. Fir Street.