Region: East | Legislative District: 14 | Length: 0.00 mi. | FY 2026 Complete Streets Program (CSP) |
![]() |
Existing ConditionsThe intersection of S. Toppenish Avenue and W. 1st Avenue existing sidewalks, curb ramps, and crosswalks are non-ADA compliant and do not provide a safe route for pedestrian travel. The lane widths are over 16 feet wide and not ideal for safely crossing the street. The intersections roadway surface is deteriorating asphalt. |
Project Funding
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 175,968 | 19,552 | 195,520 |
Right of Way | 0 | 0 | 0 |
Construction | 1,353,586 | 150,399 | 1,503,985 |
Project Totals | $1,529,554 | $169,951 | $1,699,505 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
90.0% | 10.0% | 10% |
Summary of Improvements
- All design elements for this project have the overarching goal of creating a more safe and appealing intersection in an integral part of the City. The new sidewalk and curb ramps will increase accessibility by being ADA-compliant. The bulb outs will reduce lane widths of the road, making it easier and safer to cross the road in combination with the new signal and pedestrian push buttons. The reduced lane width will also help control vehicular traffic, and the new signal will ease the entire intersection into functioning smoothly. Landscaping will be incorporated into the sidewalk and bulb out design to encourage greenspace in this downtown area. Overall, this project will increase safety and accessibility for both pedestrian and vehicular traffic. This project is intended to kick-off a downtown revitalization effort to create a better and safer community.
Description of Improvements
The project includes roadway, sidewalks, bulb outs, curb ramps, crosswalks, signal with pedestrian push buttons, and landscaping improvements.