FY 2026 CSP Selections

City of College Place
Rose Street Multiuse Path Illumination
NE Ash Ave to NE Carey Ct
TIB Award Amount
$1,825,692
Region: East   |   Legislative District: 16   |   Length: 0.00 mi. FY 2026 Complete Streets Program (CSP)

Existing Conditions

The current condition of Rose Street between Ash Ave. and Carey Ct. is dark, and the lighting will help increase visibility, safety and reduce petty crimes.

Project Funding

  TIB Funds Local Funds Total Costs
Design 215,354 23,928 239,282
Right of Way 67,389 7,488 74,877
Construction 1,542,949 171,439 1,714,388
Project Totals $1,825,692 $202,855 $2,028,547

Local Match

TIB Participation Local Match Minimum Local Match
90.0% 10.0% 10%

Description of Improvements

The project will illuminate and improve the safety of the multiuse path and sidewalks along the NE Rose Street corridor from College Ave to Carey Court.