Region: East | Legislative District: 13 | Length: 1,000.00 ft. | FY 2026 Urban Active Transportation Program (ATP) |
![]() |
Existing ConditionsThere is a sidewalk gap from Washington Way S to Windsor Ave. |
Project Funding
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 28,550 | 0 | 28,550 |
Right of Way | 0 | 0 | 0 |
Construction | 221,450 | 0 | 221,450 |
Project Totals | $250,000 | $0 | $250,000 |
Local Match
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
100.0% | 0.0% | 0% |
Summary of Improvements
- Improves pedestrian safety;
- Supports economic development;
- Completes gap;
- Improves vehicle and pedestrian access
Description of Improvements
The proposed project will fill a gap in pedestrian facilities between existing sidewalk and frontage improvements (pathway) constructed by a developer.