Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Funding Cycles

FY 2025 ATP Selections

Town of Winthrop
Bridge Street Improvement Project
Riverside Ave to Bluff St
TIB Award Amount
$528,675
Region: East   |   Legislative District: 7   |   Length: 800.00 ft. FY 2025 Urban Active Transportation Program (ATP)

Existing Conditions

Winthrop does not have a non-vehicular traffic network through the town.

Project Funding

  TIB Funds Local Funds Total Costs
Design 69,134 3,639 72,773
Right of Way 0 0 0
Construction 459,541 24,186 483,727
Project Totals $528,675 $27,825 $556,500

Local Match

TIB Participation Local Match Minimum Local Match
95.0% 5.0% 5%

Description of Improvements

This project will connect sidewalk with two prior TIB projects, connecting sidewalks constructed on Bluff Street and Castle Ave.