$479,589
Region: East   |   Legislative District: 4   |   Length: 60.00 ft. FY 2025 Urban Active Transportation Program (ATP)

Existing Conditions

Since 2012, there were 10 veh-ped crashes (1 fatal, 3 serious injury) on this busy commercial corridor wotj 19,400 ADT. The street is 60 feet wide with 5 lanes, has Transit stops for Route 90 serves low-income residential neighborhood as well.

Project Funding

  TIB Funds Local Funds Total Costs
Design 51,384 19,983 71,367
Right of Way 0 0 0
Construction 428,204 166,525 594,729
Project Totals $479,589 $186,507 $666,096

Local Match

TIB Participation Local Match Minimum Local Match
72.0% 28.0% 20%

Description of Improvements

Two new marked crossings with pedestrian refuge islands and rectangular rapid flashing beacon signals are proposed at the mid-way points between the existing signalized intersections at Custer Rd. and at Fancher Rd.