The pavement condition rating of Cascade Drive - Dam Access Rd to Kidney Lake Rd 77
Projects — TIB Project Information
TIB Project Information
City of North Bonneville's FY 2022 Seal Coat Project
2-W-973(003)-1
2-W-973(003)-1
FY 2022 Seal Coat Project
Multiple Locations
FY 2022 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $100,740
County: Skamania | Legislative District: 14 | Project Length: 0.61 | TIB Engineer: Chris Langhoff | Last Payment Date: 11/01/2021
Project Information
Lead Agency | NORTH BONNEVILLE |
Funding Year | 2022 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 14 |
Congressional District | 3 |
Federal Route Number | B301 |
Project Length | 0.61 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Brian Sabo |
Contact Email | brians@northbonneville.net |
TIB Engineer | Chris Langhoff |
Last Payment Date | 11/01/2021 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2020 | |
Delayed Project Date | 07/01/2023 | |
Predesign Approval | ||
Design Approval | 02/01/2021 | 01/11/2021 |
Bid Auth. Approval | 05/01/2021 | 05/13/2021 |
Construction Approval | 06/01/2021 | 06/17/2021 |
Project Closeout | 12/31/2021 | 10/15/2021 |
Audit Date | 11/01/2021 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 6,325 | 7,025 |
Right of Way | 0 | 0 |
Total Design | 6,325 | 7,025 |
Construction Engineering | 2,850 | 2,975 |
Construction Contract | 64,469 | 96,510 |
Other Construction | 0 | 0 |
Total Construction | 67,319 | 99,485 |
Funding Increase | 27,096 | |
Total TIB Funding | 100,740 | 106,510 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
NORTH BONNEVILLE | 5,770 | 5.4% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 5,770 | 5.4% |
Project Description
Scrub and chip seal
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |