Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of North Bonneville's FY 2019 Seal Coat Project

2-W-973(002)-1

2-W-973(002)-1
FY 2019 Seal Coat Project

Multiple Locations

FY 2019 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $34,928

County: Skamania   |   Legislative District: 14   |   Project Length: 0.52   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 01/30/2019

Project Information

Lead Agency NORTH BONNEVILLE
Funding Year 2019
Program SCPP
Current Phase Audit
Legislative District 14
Congressional District 3
Federal Route Number 9999
Project Length 0.52 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact D Sam Hughes
Contact Email sam@northbonneville.net
TIB Engineer Chris Langhoff
Last Payment Date 01/30/2019

Project Schedule

  Target Date Actual Date
Project Selection Date   11/17/2017
Delayed Project Date 07/01/2020  
Predesign Approval
Design Approval 01/01/2018 12/11/2017
Bid Auth. Approval 04/01/2018 12/11/2017
Construction Approval 05/01/2018 12/11/2017
Project Closeout 10/31/2018 01/24/2019
Audit Date   01/30/2019
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 45,247 34,928
Other Construction 0 0
Total Construction 45,247 34,928
     
Funding Surplus - 10,319  
Total TIB Funding 34,928 34,928

Local Funding Partners

Funding Amount Percent
NORTH BONNEVILLE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Chip Seal segments of Sun Tillikum, Celilo, and Pioneer Drive.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments