City of Raymond's 2024 SW Raymond Overlay

2-W-971(004)-1

2-W-971(004)-1
2024 SW Raymond Overlay

Multiple Locations

FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $373,059

County: Pacific   |   Legislative District: 19   |   Project Length: 0.67   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 01/09/2025

Project Information

Lead Agency RAYMOND
Funding Year 2025
Program SCPP
Current Phase Audit
Legislative District 19
Congressional District 3
Federal Route Number 9999
Project Length 0.67 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Scott Pearson
Contact Email raymondpw@cityofraymond.com
TIB Engineer Chris Langhoff
Last Payment Date 01/09/2025

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
Predesign Approval
Design Approval 01/02/2024 12/13/2023
Bid Auth. Approval 06/26/2024 06/20/2024
Construction Approval 08/15/2024 08/15/2024
Project Closeout 12/31/2024 01/09/2025
Audit Date   01/09/2025
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 65,048 68,459
Right of Way 0 0
Total Design 65,048 68,459
     
Construction Engineering 65,048 21,024
Construction Contract 433,648 303,208
Other Construction 0 0
Total Construction 498,696 324,232
     
Funding Increase 4,409  
Funding Surplus - 195,094  
Total TIB Funding 373,059 392,691

Local Funding Partners

Funding Amount Percent
RAYMOND 19,632 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 19,632 5.0%

Project Description

2 inch overlay

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.