Projects — TIB Project Information
TIB Project Information
City of Montesano's 2024 Chip Seal
2-W-957(016)-1
2-W-957(016)-1
2024 Chip Seal
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $202,107
County: Grays Harbor | Legislative District: 24 | Project Length: 1.23 | TIB Engineer: Chris Langhoff | Last Payment Date: 08/14/2024
Project Information
Lead Agency | MONTESANO |
Funding Year | 2025 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 24 |
Congressional District | 6 |
Federal Route Number | 9999 |
Project Length | 1.23 mi. |
ADT | 0 |
Functional Class | Principal |
Type of Work | Resurfacing |
Project Contact | Mike Olden |
Contact Email | molden@montesano.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 08/14/2024 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 01/01/2025 | |
Predesign Approval | ||
Design Approval | 01/15/2024 | 12/19/2023 |
Bid Auth. Approval | 07/15/2024 | 05/17/2024 |
Construction Approval | 06/15/2024 | 06/12/2024 |
Project Closeout | 08/20/2024 | 08/13/2024 |
Audit Date | 08/14/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 216,000 | 215,861 |
Other Construction | 0 | 0 |
Total Construction | 216,000 | 215,861 |
Funding Surplus | - 13,893 | |
Total TIB Funding | 202,107 | 215,861 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MONTESANO | 13,754 | 6.4% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 13,754 | 6.4% |
Project Description
Apply Chip Seal and fog seal to the existing road surface.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |