Many of our streets have the potential to be seal coated with chip seal for preservation, but there are portions of these streets that need significant pre-level work with HMA. The HMA prelevel work should be done at least year prior to the seal coat because fresh HMA tends to adsorb the oil to quickly, which results in poor adherence of the rock chips.
Projects — TIB Project Information
TIB Project Information
City of Montesano's 2024 Street Maintenance
2-W-957(014)-1
2-W-957(014)-1
2024 Street Maintenance
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $87,415
County: Grays Harbor | Legislative District: 24 | Project Length: 0.00 | TIB Engineer: Chris Langhoff | Last Payment Date: 07/15/2024
Project Information
Lead Agency | MONTESANO |
Funding Year | 2025 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 24 |
Congressional District | 6 |
Federal Route Number | 9999 |
Project Length | 0.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Mike Olden |
Contact Email | molden@montesano.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 07/15/2024 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
Predesign Approval | ||
Design Approval | 02/01/2024 | 12/19/2023 |
Bid Auth. Approval | 07/01/2024 | 04/26/2024 |
Construction Approval | 05/15/2024 | 05/13/2024 |
Project Closeout | 08/30/2024 | 07/14/2024 |
Audit Date | 07/15/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 64,600 | 92,015 |
Other Construction | 0 | 0 |
Total Construction | 64,600 | 92,015 |
Funding Increase | 22,815 | |
Total TIB Funding | 87,415 | 92,015 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MONTESANO | 4,600 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 4,600 | 5.0% |
Project Description
Prelevel streets at least one year in advance of a chip seal project. Current City priorities for future prelevel work are on Cedar, Park, Glenn and 3rd Avenues. All areas are not reasonably expected to be funded in one year and are a continuation of previous work.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |