Projects — TIB Project Information
TIB Project Information
City of Castle Rock's Seal Coat Project
2-W-952(001)-1
2-W-952(001)-1
Seal Coat Project
City of Castle Rock
FY 2007 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $37,952
County: Cowlitz | Legislative District: 20 | Project Length: 0.70 | TIB Engineer: Chris Langhoff | Last Payment Date: 01/16/2007
Project Information
Lead Agency | CASTLE ROCK |
Funding Year | 2007 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.70 mi. |
ADT | 150 |
Functional Class | Local Access |
Type of Work | Resurfacing |
Project Contact | David Vorse |
Contact Email | crpwd@ci.castle-rock.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 01/16/2007 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 01/27/2006 | |
Delayed Project Date | 07/01/2008 | |
Predesign Approval | ||
Design Approval | 01/27/2006 | |
Bid Auth. Approval | 01/27/2006 | 01/27/2006 |
Construction Approval | 07/01/2006 | 01/27/2006 |
Project Closeout | 02/01/2007 | 01/16/2007 |
Audit Date | 01/16/2007 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 54,804 | 37,952 |
Other Construction | 0 | 0 |
Total Construction | 54,804 | 37,952 |
Funding Surplus | - 16,852 | |
Total TIB Funding | 37,952 | 37,952 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CASTLE ROCK | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Small City Preservation Seal Coat Project
Existing Condition
Project Benefits
- Restores Roadway Surface;
- Reduces Maintenance Costs
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |